September 1974: Meeting of
recreational trail users led by Dorothy Moore. Out of that meeting
came the concept of Perry Lake Trail and the Kansas Trails
Council.
The Kansas Trails Council fielded its
first team of pathfinders on a bitterly cold day in January,
1976---that’s when the Perry Lake Trail was born! From the beginning
the Kansas City Outdoor Club has played a major role in mustering
volunteers to do the hard manual labor of scouting, designing,
clearing, marking and maintaining a hiking trail. The first two
sections, stretching from
Slough
Creek
Park through
Longview
Park to Old Military
Trail Area were dedicated as a National Recreational Trail in April,
1978. In 1983, the pathfinders came back to
Perry
Lake, determined to add
another fifteen miles, and determined, also, to develop a network of
organizations and individuals to take care of the trail. Six years
later they put the final blue blaze and the entire 28-mile loop was
marked and ready for hiking.
Spring 1986: First clearing completed
for Section 3.
February 1987: Paint blazes on Section
3 completed.
April 1987: First clearing of Section
4 occurred in April and throughout the Spring of ’87.
October 1987: Paint blazes completed
on Section 4 between Ferguson
Road and
82nd
St.
February 1988: Paint blazes complete
on Section 4 between Ferguson
Road and
Slough
Creek
Park.
April 1988: Paint blazes completed on
Section 4 along road.
November 1988: Paint blazes completed
on Section 3 along Old Well
Road (Kiowa
Rd).
2/28/1991: Richard Douthit signs on as Trail
Coordinator at Perry.
April 12.1991: Letter from Richard
Douthit to KTC board RE: whether or not to permit mountain bikes on
Perry Lake Trail.
9/16/1991: Letter from Frank Funk, Project
Manager, to Richard Douthit RE: decision not to allow mountain bikes
on Perry Lake Trail.
3/27/1992: Volunteer meeting with Mobe, Richard
Douthit and existing Trailwatchers to introduce Steve Hassler and
Kevin Otterman as new Trailwatchers at Perry.
4/3/1992: Report compiled by Richard Douthit to
Frank Funk included the following data…
1983-1988: 1014 hours for new trail
construction
$7536.90
1988: routine maintenance and redesign
work (398 hrs)
$2375.50
1989: routine maintenance and redesign
work (260 hrs)
$1656.20
1990: routine maintenance (208
hrs)
$1522.64
1991: routine maintenance
Coordinator (35 hrs)
$521.85
Trailwatchers (36 hrs)
$232.92
Trailbuilders (158 hrs) $671.50
$1426.27
$14517.51
10/17/1992: Trailbuilding workshop at
Longview
Park, led by Richard
Douthit. Cleared the spur trail to access a Hiker’s Campground with
seven campsites. Each site provided a table and a rock fire ring,
and was separated from other sites by at least
20-30’
10/18/1992: Volunteers camped the weekend at
Old Military Trail for the trailbuilding workshop above. The
Trailhead at Old Military Trail was relocated from an erosion area
to an area about 20’ east at the corner of the parking
lot.
1993: Coordinator: Richard Douthit;
Trailwatcher Section1: Jim Jackson; Trailwatcher Section 2: Kevin
Otterman; Trailwatcher Section3: Steve Hassler; Trailwatcher Section
4: Don Morford; Project Manager: Frank Funk; Park Manager: Dennis
Archer.
1993: In that year crews from Kansas
City Outdoor Club, Kanza Group of Sierra Club, and various informal
groups called in by the Coordinator or Trailwatchers spent 328 hours
at hard labor on the trail. Over the preceding then years the new
Sections 3 and 4, plus routine maintenance cost these hardy
volunteers 2688 hrs of labor, worth almost $20,000 at the going
rate---a gift from these trail lovers to the people of
Kansas.
March
8, 1993: Letter from Richard Douthit to Don Morford
(section 4 trailwatcher) RE: reroute of Section 4 near
Ferguson Road.
The original route of Section 4 east and north of
Ferguson Road
was moved away from the lake due to nesting eagle pairs on the
Slough Creek arm. Letter included maps of original and proposed
route.
November 1993: Jim Jackson let a work
crew which began on top of the hill at Devil’s Gap Trailhead and
made a loop down to the picnic grounds.
November 1993: Steve Hassler led a
Sierra Club crew on Section 3, with Kevin Otterman doing the big bow
saw work. Attendance on that outing was 13, including above and
Richard Douthit.
December 1993: A total of six eagles,
two adults and four younger ones, were observed on Section 2 near
Solitude Point.
February 1994: Dorothy Moore is
announced at the Coordinator for Perry Lake Trail, replacing Richard
Douthit. The trailwatchers consist of: Jim Jackson, Section1; Kevin
Otterman, Section 2, Steve Hassler, Section 3; John Haynes, Section
4.
3/19/94: Steve Hassler led a Kanza Sierra Club
work crew on Section 3.
3/29/11994: A GPS trail mapping project was
conducted on Section 3, utilizing a base station GPS survey unit and
a field unit. Initial results showed a trail mileage from 3.87 miles
from OMT to Kiowa
Road. The trailhead at OMT was later
rerouted to the southeast.
1/28/1995: Seven bald eagles were observed on
the Little Slough Creek arm of the lake along the hiking trail. An
active beaver lodge was also observed in the cove below Solitude
Point.
3/17/1995: After multiple outings spanning from
11/19/94 thru
1/28/95, the
first GPS trail mapping project was completed on Section 2. In
addition to GPS trail mapping, the project grew to include GIS data
collection: cataloging remaining driftwood locations on the trail
from the flood of ’93, cataloging deadfall locations for removal by
Corps personnel and marking points of interest for a future trail
brochure. Bridge crossings were also identified at that time for the
first site within OMT and the second site at
Old Quarry
Road.
Letter from Mobe, 2/15/96: Park Manager
Dennis Archer replaced by Natural Resources Specialist Barbara
“Bunnie” Watkins, who will take a more active role with the
trail.
Week of 3/3/96: Volunteer meeting with trailwatchers
and COE staff
We lost our friend and mentor, Richard
Douthit, on Christmas Day, 1996.
First week of March, 1997: Volunteer
meeting wth trailwatchers and COE staff. Jim Jackson resigned from
Section1 and was replaced by Dave Brackey.
Fall 1997: Maintenance activities on
Section 2 were over 62 manhours including setting the bridge pillars
for the OMT bridge.
11/1/97: Sierra Club Maintenance Outing. Small
crew devoted manpower to finishing the OMT bridge. Bridge work crew
included Carl and Barb Ringler, and Kevin
Otterman.
Spring 1998: Maintenance activities on
Section 2 were over 30 manhours including a reroute of Section 2 in
the vicinity of the current Richard Douthit park bench
site.
1/31/98: Sierra Club Maintenance Outing. Sierra
club crew worked on the reroute above on Section 2 near the current
site of Richard Douthit park bench.